Theory |
|
|
18 February - 24 February |
Expected Learning Outcome |
|
|
Surveying |
|
|
Principles of surveying |
|
|
Classification of surveying |
|
|
Classification based upon the nature of the field of survey |
|
|
Classification based on the Instruments |
|
|
Chaining;Instruments used for chaining |
|
|
Chaining - Instruments used for chaining - Chain |
|
|
Types of chain - Metric chain |
|
|
Types of chain - Gunter’s chain & Engineer’s chain |
|
|
Types of chain - Revenue chain & Steel band |
|
|
Chaining - Instruments used for chaining - Tapes |
|
|
Types of Tapes - Cloth Tape & Metallic tape |
|
|
Types of Tapes - Steel Tape & Invar tape |
|
|
Chaining - Instruments used for chaining - Ranging rods |
|
|
Chaining - Instruments used for chaining - Pegs & plumb bob |
|
|
Ranging of survey line |
|
|
Ranging - Code of Signals for Ranging |
|
|
Methods of ranging - Direct Ranging |
|
|
Indirect ranging |
|
|
Chaining - Chaining on uneven or sloping ground |
|
|
Lining and marking |
|
|
Methods of sloping ground - Direct Method |
|
|
Methods of sloping ground - Indirect Method |
|
|
Calculation of the horizontal distance of sloping ground |
|
|
Chain surveying |
|
|
Chain surveying - Instruments used for setting out right angles |
|
|
Instruments used for setting out right angles - Open cross staff |
|
|
Instruments used for setting out right angles - French cross staff |
|
|
Instruments used for setting out right angles - Setting out right angle |
|
|
Chain surveying - Conditions to be fulfilled by survey stations/survey lines |
|
|
Chain surveying - Off-sets |
|
|
Chain surveying - Off-sets - Surveying steps |
|
|
Basic Problems in chaining - To erect a perpendicular to a chain line |
|
|
Basic problems in chaining - To drop a perpendicular to chain line |
|
|
Basic Problems in chaining - To run a parallel to chain |
|
|
Chain surveying - Obstacle to chaining and ranging |
|
|
Obstacle to chaining and ranging - Obstacle to ranging but not chaining |
|
|
Obstacle to chaining and ranging - Obstacle to chaining but not ranging |
|
|
Obstacle to chaining but not ranging 2 |
|
|
Obstacle to chaining and ranging - Obstacle to both chaining and ranging |
|
|
Compass surveying - Introduction |
|
|
Compass surveying - Introduction - Traverse survey |
|
|
Introduction - Bearing and angles |
|
|
Compass surveying - Systems of angular measurement |
|
|
Systems of angular measurement - Meridian |
|
|
Meridian - True meridian |
|
|
Meridian - Magnetic meridian |
|
|
Meridian - Arbitrary meridian |
|
|
Compass surveying - Whole circle bearing system and Reduced bearing system |
|
|
The whole circle bearing system |
|
|
The reduced bearing system |
|
|
conversion of whole circle bearing system - Table1 |
|
|
conversion of reduced bearing system - Table2 |
|
|
Compass surveying - Fore bearing and Back bearing |
|
|
Compass surveying - Calculation of angle from bearings |
|
|
Compass surveying - Calculation of bearings from the angles |
|
|
Compass surveying - Theory of magnetic compass |
|
|
Compass surveying - The prismatic compass |
|
|
Compass surveying - Adjustment of prismatic compass |
|
|
Compass surveying - Problem-1 |
|
|
Compass surveying - Problem-2 |
|
|
Levelling - Definition |
|
|
Levelling - Methods of levelling |
|
|
Levelling - Levelling instruments: |
|
|
Levelling - Terms and abbreviations |
|
|
Levelling - Types of spirit levelling |
|
|
Find out the elevation of points using different methods |
|
|
Find out the elevation of points using different methods - Booking and Reducing Levels |
|
|
Booking and Reducing Levels - Height of Instrument method |
|
|
Booking and Reducing Levels - Rise and Fall method |
|
|
Rise and Fall method - Problems |
|
|
Levelling Staff - Classification |
|
|
Levelling Staff - Self reading staff |
|
|
Self reading staff - Folding staff |
|
|
Self reading staff -Telescopic staff |
|
|
Levelling Staff - Folding level staff in metric units |
|
|
Adjustment of a level |
|
|
Adjustment of a level - Elimination of parallax |
|
|
Plane table surveying - Definition |
|
|
Plane table surveying - Instruments |
|
|
Plane table surveying - Instruments - I |
|
|
Plane table surveying - Instruments - II |
|
|
Plane table surveying - Working operations |
|
|
Orientation - Methods |
|
|
Plane table surveying - Methods of plane tabling |
|
|
Methods of plane tabling - Radiation |
|
|
Methods of plane tabling - Intersection |
|
|
Contour surveying - Definition |
|
|
Contour surveying - Contour interval |
|
|
Contour surveying - Characteristics of contour |
|
|
Contour surveying - Methods of locating contours |
|
|
Methods of locating contours - Direct method |
|
|
Methods of locating contours - Indirect method |
|
|
Contour surveying - Interpolation of contour |
|
|
Contour surveying - Uses of contour |
|
|
25 February - 3 March |
Expected Learning Outcome |
|
|
Fish Farm-Definition |
|
|
Fish Farm - Objectives |
|
|
Fish Farm - Types |
|
|
Fish Farm - Types |
|
|
Selection of site for Aquafarm - Site selection criteria |
|
|
Selection of site for Aquafarm - Site selection |
|
|
Selection of site for Aquafarm - Reconnaissance survey |
|
|
Selection of site for Aquafarm - Accessibility |
|
|
Selection of site for Aquafarm - Physical features |
|
|
Selection of site for Aquafarm - Soil characteristics |
|
|
Selection of site for Aquafarm - Water Source |
|
|
Detailed survey |
|
|
Detailed survey - Main factors |
|
|
Detailed survey - Main factors - Topography |
|
|
Detailed survey - Main factors - Soil Characteristics |
|
|
Detailed survey - Main factors - Water Properties |
|
|
Detailed survey - Other factors - Environmental condition |
|
|
Detailed survey - Other factors - Socio-Economic condition |
|
|
Detailed survey - Other factors - Pollution |
|
|
Detailed survey - Other factors - Availablematerial |
|
|
Detailed survey - Other factors - Technical guidance |
|
|
Ponds - Definition |
|
|
Ponds - Classification based on construction |
|
|
Ponds - Classification based on source of water - sunken ponds |
|
|
Ponds - Classification based on source of water - Barrage ponds |
|
|
Ponds - Classification based on source of water - Diversion ponds |
|
|
Ponds - Classification based on source of water - Rosary system |
|
|
Ponds - Classification based on source of water - Parallel system |
|
|
4 March - 10 March |
Expected Learning Outcome |
|
|
Soil and its properties - Definition |
|
|
Soil and its properties - Classification |
|
|
Soil and its properties - Particle size classification |
|
|
Soil and its properties - Textural classification |
|
|
Soil and its properties - Highway research board classification |
|
|
Soil and its properties - Unified soil classification |
|
|
Soil and its properties - Classification - Gravels and Sands |
|
|
Soil Sampling - Definition |
|
|
Soil sampling - types |
|
|
Soil sampling - types - Disturbed sample |
|
|
Soil sampling - types - Undisturbed sample |
|
|
Soil sampling - Three phase system of soil |
|
|
Soil properties - Definitions |
|
|
Soil properties - Permeability of soil |
|
|
Soil properties - Necessity of studying permeability |
|
|
11 March - 17 March |
Expected Learning Outcome |
|
|
Lay out planning of aquafarm - Classification |
|
|
Lay out planning of aquafarm - classification - Lay out planning |
|
|
Lay out planning of aquafarm - classification - Man power planning |
|
|
Lay out planning of aquafarm - classification - Materials planning |
|
|
Layout planning of fish ponds - Classification based on culture |
|
|
Lay out planning of aquafarm - Classification - Nursing ponds |
|
|
Lay out planning of aquafarm - Classification - Rearing ponds |
|
|
Lay out planning of aquafarm - Classification - Stocking ponds |
|
|
Lay out planning of aquafarm - Important points |
|
|
Lay out planning of aquafarm - Different types of allocations |
|
|
Lay out planning of aquafarm - Square and rectangular ponds |
|
|
Lay out planning of aquafarm - Large and small ponds |
|
|
Design of ponds - Pond Geometry |
|
|
Design of ponds - Depth of pond |
|
|
Design of ponds - Top Width |
|
|
Design of ponds - Side slope |
|
|
Design of ponds - Bottom slope of pond |
|
|
Dykes - Definition |
|
|
Dykes - Height of the dyke |
|
|
Dykes - Depth of water |
|
|
Dykes - Free board |
|
|
Dykes - Wave allowance |
|
|
Dykes - Settlement allowance |
|
|
Dykes - Frost action |
|
|
Dykes - Problem |
|
|
18 March - 24 March |
Expected Learning Outcome |
|
|
Construction of ponds - Introduction |
|
|
Construction of ponds - Survey of site |
|
|
Construction of ponds - Land clearing |
|
|
Construction of ponds - Land Marking |
|
|
Construction of ponds - Excavation of soil |
|
|
Construction of ponds - Construction of drainage systems |
|
|
Construction of ponds - Construction of dykes |
|
|
Construction of ponds - Construction of dykes-Water inlet structures |
|
|
Construction of ponds - Lining of ponds and dyke |
|
|
Maintenance of ponds - Pond drainage system |
|
|
Maintenance of ponds - Seepage and its control |
|
|
Seepage and its control - Clay puddling |
|
|
Seepage and its control - Brick lining |
|
|
Seepage and its control - Plastic lining |
|
|
Maintenance of ponds - Evaporation |
|
|
Maintenance of ponds - Erosion of soil in dykes and its control |
|
|
Maintenance of ponds - Problem |
|
|
25 March - 31 March |
Expected Learning Outcome |
|
|
Calculation of area - The area of the trapezium |
|
|
Calculation of area - The area of the triangle |
|
|
Calculation of area - The area of a square |
|
|
Calculation of area - The area of a circle |
|
|
Calculation of area - Problem 1 |
|
|
Calculation of area - Problem 2 |
|
|
Calculation of area - Problem 3 |
|
|
Calculation of area - Problem 4 |
|
|
Irregular Rectilinear Figures - Problem 1 |
|
|
Irregular Rectilinear Figures - Problem 2 |
|
|
Irregular Rectilinear Figures - Problem 3 |
|
|
Irregular Rectilinear Figures - Problem 4 |
|
|
Irregular Rectilinear Figures - Problem 5 |
|
|
Calculation of area of irregular plane surfaces - Trapezoidal rule |
|
|
Calculation of area of irregular plane surfaces - Simpson’s I |
|
|
Calculation of area of irregular plane surfaces - Simpson’s II |
|
|
Calculation of area of irregular plane surfaces - Problem 1 |
|
|
Calculation of area of irregular plane surfaces - Problem 2 |
|
|
Calculation of area of irregular plane surfaces - Problem 3 |
|
|
Calculation of area of irregular plane surfaces - Problem 4 |
|
|
Calculation of volume - Calculation of volume of regular surfaces |
|
|
Calculation of volume - Volume of a triangular prism |
|
|
Calculation of volume - Volume of a cube |
|
|
Calculation of volume - Volume of a cylinder |
|
|
Calculation of volume - Problem 1 |
|
|
Calculation of volume - Problem 2 |
|
|
Calculation of volume - Problem 3 |
|
|
Calculation of volume - Calculation of volume of irregular surfaces |
|
|
Calculation of volume of irregular surfaces - Simpson’s I |
|
|
Calculation of volume of irregular surfaces - Simpson’s II |
|
|
Calculation of volume of earth work as applied to stacks and heaps - Problem 1 |
|
|
Calculation of volume of regular shape as applied to volume of pond |
|
|
Calculation of volume of regular shape as applied to volume of pond - Problem 1 |
|
|
Calculation of volume of regular shape as applied to volume of pond - Problem 2 |
|
|
Calculation of volume of regular shape as applied to volume of pond - Problem 3 |
|
|
1 April - 7 April |
Expected Learning Outcome |
|
|
Methods used to calculate volume of earthwork - Excavation and Embankment |
|
|
Longitudinal slope and cross slope |
|
|
Methods of computing the volume of earth work - Mid sectional area method |
|
|
Methods of computing the volume of earth work - Mean sectional area method |
|
|
Methods of computing the volume of earth work - Trapezoidal formula method |
|
|
Methods of computing the volume of earth work - Prismoidal formula method |
|
|
Calculation of volume of earth work as applied to roads and channels - Problem 1 |
|
|
Calculation of volume of earth work as applied to roads and channels - Problem 2 |
|
|
Calculation of volume of earth work as applied to roads and channels - Problem 3 |
|
|
8 April - 14 April |
Expected Learning Outcome |
|
|
Brackish water fish farms - Definition |
|
|
Brackish water fish farms - Classification of ponds |
|
|
Classification of ponds - Tide fed farms |
|
|
Classification of ponds - Pump fed farms |
|
|
Classification of ponds - Tide-cum pump fed farms |
|
|
Site selection for Brackish water fish farms |
|
|
Site selection for Brackish water fish farms - Topography and Tidal amplitude |
|
|
Site selection for Brackish water fish farms - Availability of active tidal creek resources |
|
|
Site selection for Brackish water fish farms - Existence and density of mangrove vegetation |
|
|
Site selection for Brackish water fish farms - High flood levels |
|
|
Site selection for Brackish water fish farms - Range of tidal variations |
|
|
Site selection for Brackish water fish farms - Type of soil and its quality |
|
|
Site selection for Brackish water fish farms - Water sources |
|
|
Water sources - Freshwater Resources |
|
|
Water sources - Brackishwater Resources |
|
|
Marine water fish farms - Definition |
|
|
Marine water fish farms - Site selection |
|
|
Marine water fish farms - Pond dyke |
|
|
Pond dyke - Main or peripheral dike |
|
|
Pond dyke - Partition dyke or secondary dyke |
|
|
Marine water fish farms - Problem 1 |
|
|
Marine water fish farms - Problem 2 |
|
|
Marine water fish farms - Creeks and estuarine |
|
|
Creeks and estuarine - Types of estuaries |
|
|
Marine water fish farms - Marine water source utilization |
|
|
15 April - 21 April |
Expected Learning Outcome |
|
|
Fresh water prawn hatchery |
|
|
Fresh water prawn hatchery - Site selection |
|
|
Fresh water prawn hatchery - Infrastructural facilities |
|
|
Infrastructural facilities - Brood stock ponds |
|
|
Infrastructural facilities - Water supply system |
|
|
Infrastructural facilities - Main hatchery complex |
|
|
Infrastructural facilities - Brood stock unit |
|
|
Infrastructural facilities - Berried female holding tanks |
|
|
Infrastructural facilities - Hatching tanks |
|
|
Infrastructural facilities - Larval rearing unit |
|
|
Infrastructural facilities - Atermia hatching unit |
|
|
Design of Hatcheries |
|
|
Design of Hatcheries - Design of brood stock ponds |
|
|
Design of Hatcheries - Brood stock raising units |
|
|
Design of Hatcheries - Larval rearing unit |
|
|
Design of Hatcheries - Atermia hatching tanks |
|
|
Design of Hatcheries - Sheds |
|
|
Water requirements and storage tanks - Brackish water |
|
|
Water requirements and storage tanks - Sea Water |
|
|
Water requirements and storage tanks - Fresh water |
|
|
Water requirements and storage tanks - Over head tanks |
|
|
Water requirements and storage tanks - Other facilities |
|
|
22 April - 28 April |
Expected Learning Outcome |
|
|
Race way system - Definition |
|
|
Race way system - Advantages and disadvantages of this system |
|
|
Race way system - Site selection and Layout plan of raceway culture |
|
|
Race way system - Construction materials |
|
|
Race way system - Water supply system |
|
|
Types of raceway culture system - With treatment and without treatment |
|
|
Types of raceway culture system - Parallel system |
|
|
Types of raceway culture system - Series system |
|
|
Types of raceway culture system - Combination of Series and parallel raceway units with water re-circulation |
|
|
29 April - 5 May |
Expected Learning Outcome |
|
|
Water supply systems - canals |
|
|
Water control structures or Gates |
|
|
Computation of discharge through sluices |
|
|
Water supply systems - Types of canals |
|
|
Canals - Formula to calculate the cross-sectional area |
|
|
Water supply systems - Canals - Pipeline |
|
|
Water supply systems - Canals - Types of pipe |
|
|
Water supply systems - Canals - Water budget for pond |
|
|
Design of Canals - Feeder channel |
|
|
Design of Canals - Terminology |
|
|
Design of Canals - Design of side slope and bottom slope of the channel |
|
|
Design of Canals - Channel of most economical cross section |
|
|
Design of Canals - Design of feeder channel |
|
|
Design of Canals - Determination of non- erodible and erodible channel section dimensions |
|
|
Design of Canals - Determination of erodible channel section dimensions |
|
|
Water control structures or Gates - Definition |
|
|
Water control structures or Gates - Main gate |
|
|
Water control structures or Gates - Main gate 2 |
|
|
Water control structures or Gates - Secondary gates |
|
|
Water control structures or Gates - Pond inlet gates |
|
|
Water control structures or Gates - Pond inlet gates 2 |
|
|
Water control structures or Gates - Open type pond inlet structure |
|
|
Water control structures or Gates - Computation of discharge through sluices |
|
|
Computation of discharge through sluices - Under free flow condition |
|
|
Computation of discharge through sluices - Under free flow condition |
|
|
Computation of discharge through sluices - Under free flow condition - Cd values |
|
|
Computation of discharge through sluices - Submerged flow condition |
|
|
Computation of discharge through sluices - Under partially submerged flow condition |
|
|
6 May - 12 May |
Expected Learning Outcome |
|
|
Aerators - Definition |
|
|
Aerators - Purpose of aeration |
|
|
Aerators - Principle of aeration |
|
|
Aerators - Types of aerators |
|
|
Aerators - Types of aerators - Gravity aerators |
|
|
Types of aerators - Gravity aerators - Perforated tray model |
|
|
Types of aerators - Gravity aerators - Gravity driven paddle wheel model |
|
|
Types of aerators - Gravity aerators - Plastic rings or wheel model |
|
|
Types of aerators - Surface Aerators |
|
|
Types of aerators - Surface Aerators - Nozzles |
|
|
Types of aerators - Surface Aerators - Spray aerators |
|
|
Types of aerators - Surface Aerators - Floating paddle wheel aerators |
|
|
Types of aerators - Turbine Aerators |
|
|
Types of aerators - Cascades or Falls |
|
|
Aerators - Placement of the aerators |
|
|
Pumps - Definition |
|
|
Pumps - Purpose of pumping |
|
|
Pumps - Choice of pump |
|
|
Pumps - Classification of Pumps |
|
|
Pumps - Points to be considered for design of pumping station |
|
|
Pumps - Points to be considered for design of pumping station_2 |
|
|
Pumps - Computation of Horse power requirement of the motor driving the pump |
|
|
Pumps - Computation of water requirement |
|
|
Pumps - Computation of water requirement - Problem 1 |
|
|
Filtration - Definition |
|
|
Filtration - Classification according to form of materials |
|
|
Filtration - Classification - Mechanical Filters |
|
|
Mechanical filters - Stationary screens |
|
|
Mechanical filters - Rotary screens |
|
|
Rotary screens - Axial flow rotary screens |
|
|
Rotary screens - Radial flow rotary screens |
|
|
Rotary screens - Chain type rotary screen |
|
|
Rotary screens - Vibratory screens |
|
|
Filtration - Classification - Sand Filters |
|
|
Sand filters - Types |
|
|
Filtration - Classification - Gravitational separation |
|
|
Filtration - Classification - Biological filters |
|
|
20 May - 26 May |
Experiment No 1 - Folding and unfolding of chain |
|
|
Experiment No 2 - Line marking |
|
|
Experiment No 3 - Ranging |
|
|
Experiment No 4 - To erect a perpendicular to chain line |
|
|
Experiment No 5 - To run a parallel to chain line through a given point |
|
|
27 May - 2 June |
Experiment No 1 - Obstacle to chaining and ranging |
|
|
Experiment No 2 - Obstacle to chaining but not ranging |
|
|
Experiment No 3 - Obstacle to both chaining and ranging |
|
|
3 June - 9 June |
Experiment No 1 - Determination of area of a plot |
|
|
10 June - 16 June |
Experiment No 1 - Determination of distance between two points |
|
|
17 June - 23 June |
Experiment No 1 - Determination of elevation of different points |
|
|
24 June - 30 June |
Experiment No 1 - Determination of elevation between water source and pond site |
|
|
1 July - 7 July |
Experiment No 1 - Plotting of the position of objects by radiation and intersection method |
|
|
Experiment No 2 - Plotting of the position of objects by intersection method |
|
|
8 July - 14 July |
Experiment No 1 - Drawing of contour lines by direct method |
|
|
15 July - 21 July |
Experiment No 1 - Drawing of contour lines by indirect method |
|
|
22 July - 28 July |
Experiment No 1 - Earth work calculation for dyke preparation |
|
|
29 July - 4 August |
Experiment No 1 - Earth work calculation for channel making |
|
|
5 August - 11 August |
Experiment No 1 - Distribution of grain size in coarse grained soil |
|
|
12 August - 18 August |
Experiment No 1 - Lay out plan of Fish Farms |
|
|
19 August - 25 August |
Experiment No 1 - Layout drawing for water supply Systems to the fish Ponds |
|
|
26 August - 1 September |
Experiment No 1 - Design of dykes and calculation of time required for emptying the pond |
|
|
2 September - 8 September |
Experiment No 1 - Computation of horse power requirement of the motor driving the pump |
|
|
9 September - 15 September |
Experiment No 1 - Computation of water requirement for a Aquaculture pond |
|
|
16 September - 22 September |
Experiment No 1 - Lay out plan of hatcheries |
|
|
Experiment No 1 - Lay out plan of hatcheries |
|
|
23 September - 29 September |
References: |
|