Water requirements and storage tanks - Other facilities

Unit 9 - Hatcheries

Design of Hatcheries

Water requirements and storage tanks
Other facilities
Pump house (4 x 4 m) = 2 No. = 32 m2
Generator room (10 x 5) = 1 No. = 50 m2
Air-blower room (10 x 5 m) = 1 No. =500 m2
Store (10x10) = 1 No. = 100m2
Office (10x5m)=1No. = 50 m2
Staff quarters (10x5) = 10 No. = 500 m2
Total = 782m2

Note :
The above calculations have been made on the basis of the existing technology with an average survival of 25% from stage I Larvae to post Larvae (PL 5-10). With the same infrastructural facilities the production may increase by 50% (i.e., 15 million per annum)