This type of terracing is commonly adopted over R.C.C. roofing. Below are the steps of how the terracing is laid:
The R.C. slab is cleaned off dust etc. land layer of hot bitumen is applied at the rate of 1.7 kg per sq. meter of roof surface.
A layer of coarse sand is immediately spread over the hot layer of bitumen, at the rate of 0.6 cubic meter of sand per 100 sq. meter of roof surface.
A 10 cm thick (average) layer of lime concrete is laid, in proper slope. The entire slope is given in lime concrete itself. The lime concrete may consists of 2 parts of lime, 2 parts of surkhi and 7 parts of brick ballast of 25 mm gauge. The concrete is well beaten.
Two courses of flat brick tiles are laid in 1: 3 cementmortar. The joints of top course are pointed with 1: 3 cement mortars. The vertical joints in the two courses are broken.