RINGER MACHINE
Aim: To seal (ring) a polythene casing stuffed with meat and record the power transmission elements of a ringer machine.
Apparatus:
Observations: Following observations have to be recorded.
Procedure:
Aim: To seal (ring) a polythene casing stuffed with meat and record the power transmission elements of a ringer machine.
Apparatus:
- Polythene casing with stuffed meat.
- Measuring scale
- Outside and inside caliper
- Tachometer
- Thread (Nylon)
Observations: Following observations have to be recorded.
Sl.No. | Parameters | |
1. | Horse power of the electrical motor (HP/KW) | |
2. | RPM of the electrical motor (rpm) | |
3. | Type of mechanism used | |
4. | Type of cam used | |
5. | No. of dies used | |
Procedure:
- Switch on the electrical motor before starting the work.
- Put the casing in between two dies.
- Take out the sealed casing.
- Switch off the machine.